campus construction initiatives

 

 

May 2010
Sponsor: Facilities (Kosiba) / Project Manager: Various NIS Staff / Health: 

  • Preparation completed for moving ~600 personnel and their equipment out of Damen, Law school renovation ongoing. Rome Center renovation started and monitored.
  • Next Steps: 1) Relocation of Damen Hall departments; 2) Complete Law School moves, Cuneo Museum upgrades; 3) Review infrastructure requirements for Resurrection Retreat Center; 4) Continue planning the Rome Center infrastructure.

March 2010
Sponsor: Facilities (Kosiba) / Project Manager: Various NIS Staff / Health: 

  • Completed 20-24 Chicago Ave. build-out and the SoC convergence Studio.
  • Next Steps: Continue efforts in Coffey Hall construction, relocation of Damen hall departments, Mundelein RDC build-out, Law School renovations, Cuneo Museum upgrades, Rome Center Renovations, and Center for Varsity Athletics planning.

December 2009
Sponsor: Facilities (Kosiba) / Project Manager: Various NIS Staff / Health: 

  • 3rd Fl Granada Center, LT 9th, 16th and 17th floors complete.
  • Next Steps: Coffey Hall, Relocation of Damen Hall departments, 20-24 classrooms build out, and School of Communication studio.

August 2009
Sponsor: Facilities (Kosiba) / Project Manager: Various NIS Staff / Health:

  • Mundelein Phase 4, Spring Hill, Crown Center 3rd and 4th floors. 
  • Next Steps: (1) 3rd Floor Granada Center, Lewis Towers 9th, 16th and 17th floors, Coffey Hall, relocation of Damen Hall departments.

May 2009
Sponsor: Facilities (Kosiba) / Project Manager: Various NIS Staff / Health:

  • Burrowes House, College of Arts and Sciences move to Sullivan, and Book store transition to Follett completed.
  • Next Steps: (1) Renovations continue of new residence hall (Spring Hill) and 3rd floor Granada Center.

March 2009
Sponsor: Facilities (Kosiba) / Project Manager: Various NIS Staff / Health:

  • Monitor project initiatives via weekly review.
  • Next Steps: (1) Continue to meet the individual milestones for each project as services are required.

November 2008
Sponsor: Facilities (Kosiba) / Project Manager: Various NIS Staff / Health:

  • The most active fall construction projects involving ITS are:

                 School of Communication
                 Law School renovation
                 Baumhart Hall 2nd and 3rd floor remodeling
                 Lawson Parking lot connectivity to LUC
                 20-24 Chicago Ave. build-out

  • Next Steps: (1) Continue to meet the individual milestones for each project as services are required.

August 2008
Sponsor: Facilities (Kosiba) / Project Manager: Various NIS Staff / Health:

  • The most active fall construction projects involving ITS are:

                 Mundeline remodeling
                 The Clare
                 Law School Renovation
                 Baumhart Hall 2nd floor remodeling
                 20-24 Chicago Ave. build-out
                 Lawson Parking Lot connectivity to LUC

  • Next Steps: (1) Continue to meet with the individual milestones for each project as services are required.

May 2008
Sponsor: Facilities (Kosiba) / Project Manager: Various NIS Staff / Health:

  • The following are the most active spring construction projects involving ITS resources:

                 Mundeline remodeling
                 Santa Clara, Lemoyne, Canisius residence halls
                 Ignatius House
                 The Clare

  • Next Steps: (1) Continue to meet with the individual milestones for each project as services are required.