Loyola University Chicago

Information Technology Services

Entrance Control for Gentile Center (PSS 598, 788)

 

 

December 2009
Sponsor: Student Affairs (Planek) / Project Manager: Biskoski (Slazyk) / Health: 

  • Completed, in production

August 2009
Sponsor: Student Affairs (Planek) / Project Manager: Biskoski (Slazyk) / Health: 

  • Completed, in production.

May 2009
Sponsor: Student Affairs (Planek) / Project Manager: Biskoski (Slazyk) / Health: 

  • Completed, in production.

March 2009
Sponsor: Student Affairs (Planek) / Project Manager: Biskoski (Slazyk) / Health: 

  • Completed, in production.
  • Clean-up in logging function.

November 2008
Sponsor: Student Affairs (Planek) / Project Manager: Biskoski (Slazyk) / Health:

  • Information extract from Loyola is ready for transmission to TIX. Procedures for TIX to receive our secure transmission are being worked out.
  • Testing of the download file is complete.
  • Handheld downloads successful, used at several basketball games.
  • Next Steps:
    (1) Test the file transfer with TIX when that protocol is worked out. Closeout project.

August 2008
Sponsor: Student Affairs (Planek) / Project Manager: Biskoski (Slazyk) / Health: 

  • TIX vendor has successfully established a connection to TouchNet for credit card processing.  They are in the process of building our seat maps.
  • Information extract from Loyola is ready for transmission to TIX.  Procedures for TIX to receive our transmission are being worked out.
  • Next steps:  (1) Test the file transfer with TIX when that protocol is worked out.  Begin verification testing.