Sponsor: Grad Admission (Roberts) / Project Manager: Pullen, Apa / Health:  

  • Restarted project
  • Met with implementation team to define requirements.
  • Next Steps: Put together potential timelines and activities list.

March 2010
Sponsor: Grad Admission (Roberts) / Project Manager: Pullen, Apa / Health:  

  • Initial meetings between EM and ITS staff to determine work effort and hardware needs. Project activity dropped as priority dropped.