May 2010
Sponsor: Student Affairs (Hale) / Project Manager: Pullen / Health: 

  • Completed phase three of project that provides professional and graduate students on-line housing applications.
  • Next Steps:
    Continue with final phase, the implementation of housing self-assign.
     

March 2010
Sponsor: Student Affairs (Hale) / Project Manager: Pullen / Health: 

  • Completed first two phases of project.
  • All student contracts are now online through the RMS web.
  • Upay site was added for online credit card deposits.
  • Next Steps:
    Continue with Phase 3 (Prof/Grad/New Grad online housing contracts) & phase 4 (implementation of housing self-assign, Feb 2011) of project.

December 2009
Sponsor: Student Affairs (Hale) / Project Manager: Pullen / Health:  

  • Completed requirement gathering document.
  • Established target implementation dates.
  • Configured application and database to test Web module.
  • Next Steps:
    Complete LDAP interface with NextStop Portal. Move configuration to production to allow incoming freshmen and transfer students to complete applications via RMS Web.

August 2009
Sponsor: Student Affairs (Hale) / Project Manager: Pullen / Health:  

  • Project moved from "HOLD" to "ACTIVE".
  • Held project kick-off meeting on August 7th.
  • Next Steps:
    (1) Complete requirement gathering documents, (2) Establish target implementation dates.

May 2009
Sponsor: Student Affairs (Hale) / Project Manager: Pullen / Health: 

  • Meeting with client monthly with clients.
  • Met with Marquette University to review how they implemented the web portion of RMS; RMS was on site for three days to train and assist in the set-up of the web portion.
  • Next Steps:
    ResLife staff to complete setup in development environment and do testing.

March 2009

Sponsor: Student Affairs (Hale) / Project Manager: TBD (Pullen) / Health: 

  • Meeting with client monthly to aid in documentation of their business process flows.
  • Next Steps:
    Client to complete documentation on process flows in preparation of RMS vendor coming on-site 4/14-4/16/2009 to set up web component.

November 2008
Sponsor: Student Affairs (Hale) / Project Manager: TBD (Pullen) / Health: 

  • Project has been reactivated; ResLife and ITS holding planning meetings to identify objectives and goals.
  • ResLife and ITS Management team met with Marquette University to discuss implementation and strategies.
  • Next Steps:
    (1) Assign Project Manager, (2) Complete business process documentation to be used by vendor for implementation, (3) Bring in RMS for three-day set-up sessions.

August 2008
Sponsor: Student Affairs (Hale) / Project Manager: Marsh (Pullen) / Health: 

  • Project has been put on hold by ResLife due to constraints in ResLife.
  • Next Steps:
    TBD.

May 2008
Sponsor: Student Affairs (Hale) / Project Manager: Roberts / Health: 

  • Project has unresolved issues regarding approach to functional configuration, maintenance and commitment to delivering project tasks in a timely fashion.
  • More progress was made on current workflow. Met to discuss issues and strategies for accommodating desired workflow in self-service application.
  • Next Steps:
    Meeting to review annual reapplication workflow.