Sponsor: Finance (Bursar) / Project Manager: Dayton (Adams) / Health:

  • Phase I is complete with successful rollout for new enrollments, billing, payments, and delinquencies. Phase II for multiple plan years and refinements has begun.
  • Next Steps: 1) Phase II on target for 8/1/2010; 2) Verification process (July) and Reconciliation of actual (Oct) are major milestones. 

March 2010
Sponsor: Finance (Bursar) / Project Manager: Dayton (Adams) / Health:

  • Most objects migrated to production. Final testing in PRE environment.
  • Communications plan in progress.
  • Next Steps: (1) Complete testing and modifications. 2) Systems testing. 3) On target for March 17 rollout to begin Plan Enrollment for 2010-11 academic year.

December 2009
Sponsor: Finance (Bursar) / Project Manager: Dayton (Adams) / Health:

  • Design and requirements gathering completed.
  • Online and batch processes coded and currently in user testing.
  • Communications plan in progress.
  • Next Steps: (1) Re-engage HR team members after year-end, (2) Systems testing, (3) On target for March 1 rollout.

August 2009
Sponsor: Finance (Bursar) / Project Manager: Dayton (Adams) / Health:

  • Design and requirements gathering completed.
  • Online process coded and currently in user testing.
  • Coding begun for batch payment synch process.
  • Next Steps: (1) Complete online testing and modifications, (2) Complete major batch processes, (3) Systems testing.

May 2009
Sponsor: Finance (Bursar) / Project Manager: Dayton (Adams) / Health:

  • Design meetings continue with Bursar staff eleven requirements gathering meetings held resulting in design decisions and refinement of business processes.
  • Next Steps: (1) Data modeling has begun and page mock-ups will begin to be created in May.

March 2009
Sponsor: Finance (Bursar) / Project Manager: Dayton (Adams) / Health:

  • High level requirements meetings.
  • Project plan drafted.
  • Next Steps: (1) Estimate staffing needs and costs; create detailed design specifications.