wellness electronic medical records - self service (Pss 802)

 

November 2008
Sponsor: Student Affairs (Asaro) / Project Manager: Prina / Health:

  • Application "Go Live" occurred in 10/3 after implementing bug fixes from vendor.
  • OpenCommunicator product is in production. Request for a development system is deferred until necessary LUC team members are available to implement.
  • Next Steps: (1) Implement development instance of OpenCommunicator. (2) Schedule project close-out.

August 2008
Sponsor: Student Affairs (Asaro) / Project Manager: Prina / Health:

  • Target Go Live date is currently 9/15, waiting on response from the vendor for two critical issues.
  • Next steps: (1) Attempt to contact vendor again and receive necessary application set-up information. (2) Reassess 9/15 target based on critical issue resolution.

May 2008
Sponsor: Student Affairs (Asaro) / Project Manager: Roberts / Health:

  • Vendor has run into another difficulty with LDAP and is working on a modification to the next release – due out on 6/4/08 – to handle the issue.
  • Next Steps: (1) Validate authentication; (2) Vendor will work with Wellness staff to configure self service and provide administrative training.