Continuing construction

Construction Update

Demolition at 14–16 E. Pearson began this summer and will continue until November.

The final phase of demolition continues, as Quinlan lays plans for a new building. The remaining demolition at 14–16 E. Pearson will continue by hand.

Due to an unforeseen mechanical failure with the drilling rig, construction will take place on Saturdays from 8 a.m.–8 p.m. throughout the month of October to ensure that the team remains on schedule.

After November 1, the south parking lane will closed to the public and foot traffic will be restricted to the north side. Structural work is also scheduled to begin in November, with sheet piling beginning at Chestnut and moving south. The construction team will push the sheets into the ground to minimize vibration.