Planned Power Outage at Select Lake Shore Campus Building

October 5, 2017

Loyola Community,

Due to electrical upgrades required for the Cudahy Library Mechanical Project, there will be a planned ComEd power outage today, October 5, at 10 p.m. The Crown Center will be impacted for approximately 15 minutes, and Cudahy Library and the Information Commons will be impacted for approximately two hours.

An additional outage is planned for Tuesday, October 10, at 8 a.m. Again, the Crown Center will be impacted for approximately 15 minutes, and Cudahy Library and the Information Commons will be impacted for approximately two hours.

Operation of both Cudahy Library and the Information Commons’ facilities will be impacted by these outages, so please check posted signage at each location for the revised hours of operation.

As always, please power down any electronic equipment, computers, etc. prior to each outage to minimize any potential impact.

Thank you,

William D. Curtin
Director of Environmental Services

Summer Construction Update

Summer Construction Update

March 27, 2017: Scaffolding on south side of Cudahy Science Hall. (Photo: Hamlet Gonzalez)

‌‌Summer 2018 Construction Update 

 

Please check back periodically for upcoming campus construction projects and impacts.

 

Health Sciences Campus Stormwater Management – Phase 1

  • Public bid, award, and preconstruction (May 1 – July 4)
  • Construction of stormwater infrastructure under Lots 3 and 5 (July 15 – November 25)
  • Construction of stormwater infrastructure under Lot 10 (April 2018 – July 2018)

 

For questions regarding campus construction, please e-mail us at facilities@luc.edu.