Loyola University Chicago

Facilities

archive

Classes and Events Resume on Tuesday in Corboy Law Center

July 9, 2018

Loyola Community,

As ComEd works toward resolving the power outage in the Corboy Law Center this evening, the University is expecting that all classes and events will resume tomorrow morning. The Lewis Library will also reopen, and faculty and staff will once again be able to access their offices.

Please check your e-mail for additional updates or changes to tomorrow’s reopening. Should the building remain closed, the University has contingency plans to ensure classes and events will continue as usual but in alternative locations.

Sincerely,

Kana Henning
Associate Vice President of Facilities

Power Outage in Corboy Law Center: Classes and Events Canceled

July 9, 2018

Loyola Community,

A power outage occurred yesterday in the Corboy Law Center on the Water Tower Campus and continues to affect the building today as ComEd works to remedy the issue. All classes and events in that building will be canceled until further notice, and classes will made up at another time. Additionally, the Lewis Library is closed, but library services are still available on the University’s other campuses and online. Offices for faculty and staff will also be inaccessible.

Please check your e-mail for additional updates today on the progress of the restoration.

Sincerely,

Kana Henning
Associate Vice President of Facilities

Planned Power Outage at Select Lake Shore Campus Building

October 5, 2017

Loyola Community,

Due to electrical upgrades required for the Cudahy Library Mechanical Project, there will be a planned ComEd power outage today, October 5, at 10 p.m. The Crown Center will be impacted for approximately 15 minutes, and Cudahy Library and the Information Commons will be impacted for approximately two hours.

An additional outage is planned for Tuesday, October 10, at 8 a.m. Again, the Crown Center will be impacted for approximately 15 minutes, and Cudahy Library and the Information Commons will be impacted for approximately two hours.

Operation of both Cudahy Library and the Information Commons’ facilities will be impacted by these outages, so please check posted signage at each location for the revised hours of operation.

As always, please power down any electronic equipment, computers, etc. prior to each outage to minimize any potential impact.

Thank you,

William D. Curtin
Director of Environmental Services

Summer Construction Update

Summer Construction Update

March 27, 2017: Scaffolding on south side of Cudahy Science Hall. (Photo: Hamlet Gonzalez)

‌‌Summer 2018 Construction Update 

 

Please check back periodically for upcoming campus construction projects and impacts.

 

Health Sciences Campus Stormwater Management – Phase 1

  • Public bid, award, and preconstruction (May 1 – July 4)
  • Construction of stormwater infrastructure under Lots 3 and 5 (July 15 – November 25)
  • Construction of stormwater infrastructure under Lot 10 (April 2018 – July 2018)

 

For questions regarding campus construction, please e-mail us at facilities@luc.edu.